TRANSPORTATION PROJECT DESCRIPTION Lockwood Valley Road MP 12.69 Emergency Repairs – Permanent Restoration ESTIMATED CONSTRUCTION COST $190,000 CONST. START DATE May 2026 CONST. END DATE July 2026 PROJECT MANAGER/ DESIGN ENGINEER Daniel Espinoza CONTACT NUMBER (805) 654-2048 Location Map – Lockwood Valley Road MP 12.69 Emergency Repairs – Permanent Restoration
TRANSPORTATION PROJECT DESCRIPTION Ventura Ave MP 0.52 Culvert Pipe Replacement ESTIMATED CONSTRUCTION COST $250,000 CONST. START DATE January 2026 CONST. END DATE February 2026 PROJECT MANAGER/ DESIGN ENGINEER Said Negm CONTACT NUMBER (805) 654-3370 Location Map – Ventura Ave MP 0.52 Culvert Pipe Replacement
TRANSPORTATION PROJECT DESCRIPTION Shekell Road Slope Repair MP 0.56 ESTIMATED CONSTRUCTION COST $75,000 CONST. START DATE September 2025 CONST. END DATE September 2025 PROJECT MANAGER/ DESIGN ENGINEER Joshua Patricio CONTACT NUMBER (805) 654-2054 Location Map – Shekell Road Slope Repair MP 0.56
Ventura County only Bilingual Newspaper June 19th 2025 By Editorial Team Supervisor Kelly Long’s Office and the Ventura County Public Works Agency (CPWA), in collaboration with community partners and local leaders, celebrated the completion of the El Rio Pedestrian Improvements Project with a ribbon cutting ceremony on Monday, June 2, 2025, at the First Baptist…
Amigos 805 May 29th, 2025 by Community Contributor VENTURA — Supervisor Kelly Long’s Office and the Ventura County Public Works Agency (VCPWA) will host a ribbon cutting ceremony to celebrate the completion of the El Rio Pedestrian Improvements Project on Monday, June 2 at 12:00 p.m. The event will take place in the parking lot of the…
TRANSPORTATION PROJECT DESCRIPTION Canada Larga Rd Storm Damage Repairs at MP 2.78 ESTIMATED CONSTRUCTION COST $260,000 CONST. START DATE August 2025 CONST. END DATE October 2025 PROJECT MANAGER/ DESIGN ENGINEER Chase Luckey CONTACT NUMBER (805) 654-2050 Location Map – Canada Larga Rd Storm Damage Repairs at MP 2.78
TRANSPORTATION PROJECT DESCRIPTION San Cayetano St Storm Damage Repair ESTIMATED CONSTRUCTION COST $30,000 CONST. START DATE August 2025 CONST. END DATE August 2025 PROJECT MANAGER/ DESIGN ENGINEER Chase Luckey CONTACT NUMBER (805) 654-2050 Location Map – San Cayetano St Storm Damage Repair
TRANSPORTATION PROJECT DESCRIPTION Pavement Resurfacing – Nyeland Acres Area ESTIMATED CONSTRUCTION COST $700,000 CONST. START DATE April 2026 CONST. END DATE June 2026 PROJECT MANAGER/ DESIGN ENGINEER Joshua Patricio CONTACT NUMBER (805) 654-2054 Location Map – Pavement Resurfacing at Nyeland Acres
Ojai Valley News By Grant Phillips January 6, 2025 The city of Camarillo will host a town hall for residents impacted by the Mountain Fire on Tuesday, Jan. 7, covering the potential for post-fire debris flow. The meeting will be hosted by the Ventura County Sheriff’s Office of Emergency Services and the city of Camarillo,…