Ventura Ave Pedestrian & Bike Lane

Upcoming Construction Activities:

      • Approximately 1,450 feet of new curb, gutter and sidewalk along the eastern portion
      • New curb ramps, bulb-outs, and driveways approaches
      • Signing and striping upgrades including high visibility crosswalks
      • Drainage improvements including approx. 225 feet of new storm drain pipe, drop inlet and catch basins
      • New Class II bike lanes and Class III bike route facilities

Construction – Start in May 2025 and end July 2025

Project Manager: Joshua Patricio (805) 654-2054