Hueneme Road Widening

Project Description:

      • Approximately 1.75 miles of roadway widening to include center turn lane and two travel lanes in each direction from Edison Dr. to Rice Ave.
      • Installs dedicated Class II buffered bike lanes
      • Installs centerline and edge line rumble strips
      • Utility relocations
      • Traffic signal modifications
      • Signing and striping upgrades
    • Current Status:
      • Environmental (NEPA & CEQA)
    • Next Steps:
      • Design and Right-of-Way anticipated 2026 (pending TCEP funding)
      • Construction anticipated 2029 (pending TCEP funding)

Project Manager: Gianfranco Laurie    (805) 654-2063