RD25-09Ventura Ave Pedestrian & Bike Lane ImprovementsGranite Construction June 20251$139,107.557/14/2025
RD25-09Ventura Ave Pedestrian & Bike Lane ImprovementsGranite Construction July 20252$408,403.239/4/2025
RD25-09Ventura Ave Pedestrian & Bike Lane ImprovementsGranite Construction August 20253$182,283.0310/7/2025
RD25-09Ventura Ave Pedestrian & Bike Lane ImprovementsGranite Construction September 2025
4$254,652.3611/3/2025
RD25-09Ventura Ave Pedestrian & Bike Lane ImprovementsGranite Construction October 20255$141,764.2511/25/2025
RD25-09Ventura Ave Pedestrian & Bike Lane ImprovementsGranite ConstructionNovember 20256$238,167.993/5/2026
RD25-09Ventura Ave Pedestrian & Bike Lane ImprovementsGranite Construction April 20267$71,809.395/14/2026
RD25-21Piru Canyon Rd Storm Drain Repairs Sam Hill & Sons August 20252$225,256.879/23/2025
RD25-21Piru Canyon Rd Storm Drain RepairsSam Hill & Sons November 20255$63,412.5012/17/2025
RD25-21Piru Canyon Rd Storm Drain RepairsSam Hill & SonsDecember 20256$152,462.171/30/2026
RD25-21Piru Canyon Rd Storm Drain RepairsSam Hill & SonsJanuary 20267$238,277.913/25/2026
RD25-21Piru Canyon Rd Storm Drain RepaisSam Hill & Sons June 20269$59,577.317/8/2026
RD26-01Guardrail UpgradesBlackPointeOctober 20251$125,011.4412/18/2025
RD26-01Guardrail UpgradesBlackPointeNovember 20252$210,721.0512/30/2025
RD26-01Guardrail UpgradesBlackPointeDecember 20253$214,073.482/11/2026
RD26-01Guardrail UpgradesBlackPointeJanuary 20264$159,046.853/2/2026
RD26-01Guardrail UpgradesBlackPointe February 20265$150,810.823/26/2026
RD26-01Guardrail UpgradesBlackPointeMarch 20266$96,364.456/29/2026
RD26-01Guardrail UpgradesBlackPointeJuly 20267$50,317.278/12/2026
RD26-02Pedestrian Crossing Enhancement Onyx PavingDecember 20251$2,850.001/30/2026
RD26-02Pedestrian Crossing Enhancement Onyx Paving January 20262$125,344.902/27/2026
RD26-02Pedestrian Crossing EnhancementOnyx Paving March 20264$170,582.005/18/2026
RD26-02Pedestrian Crossing EnhancementOnyx Paving April 20265$42,466.906/26/2026
RD26-02Pedestrian Crossing Enhancement Onyx Paving August 20266$17,960.208/25/2026
RD26-04Pavement Resurfacing - Lesser/Jenny/RuthToro EnterpriseDecember 20251$103,557.601/30/2026
RD26-04Pavement Resurfacing - Lesser/Jenny/Ruth Toro EnterpriseJanuary 20262$292,565.504/7/2026
RD26-04Pavement Resurfacing - Lesser/Jenny/Ruth Toro EnterpriseFebruary 20263$163,810.264/7/2026
RD26-04Pavement Resurfacing - Lesser/Jenny/RuthToro EnterpriseJuly 20265$79,694.848/10/2026
RD26-07(I)Canada Larga Storm Damage Repairs BSN Construction February 20261$47,181.754/16/2026
RD26-06Balcom Canyon Road Repairs @MP 5.66Toro EnterpriseDecember 20251$146,391.671/30/2026
RD26-06Balcom Canyon Road Repairs @MP 5.66Toro EnterpriseJanuary 20262$191,333.232/27/2026
RD26-06Balcom Canyon Road Repairs @MP 5.66Toro EnterpriseFebruary 20263$25,792.504/8/2026
RD26-06Balcom Canyon Road Repairs @MP 5.66Toro EnterpriseFebruary 20264$16,250.245/14/2026
RD26-06Balcom Canyon Road Repairs @MP 5.66Toro EnterpriseFebruary 20265$19,987.776/26/2026
RD26-17No Overnight Parking SignsToro EnterpriseFebruary 20261$156,835.503/25/2026
RD26-17No Overnight Parking SignsToro Enterprise March 20262$35,710.504/8/2026
RD26-21(E) Reeves Rd @MP 0.25 Emergency RepairsSummer Construction January 20261$304,724.504/14/2026
RD26-21(E) Reeves Rd @MP 0.25 Emergency Repairs Summer Construction February 20262$16,038.136/10/2026
RD26-23(E)Fraser Street Low Water Crossing Emergency RepairsSummer Construction January 20261$19,921.344/24/2026
RD26-23(E)Fraser Street Low Water Crossing Emergency Repairs Summer Construction January 20262$1,1049.496/10/2026
RD26-25Pavement Resurfacing - Nyeland AcresToro EnterpriseJune 20261$48,150.757/16/2026
RD26-25Pavement Resurfacing - Nyeland AcresToro EnterpriseAugust 20262$692,711.398/25/2026
RD26-27 Rumble Strips Toro Enterprise August 20261$323,439.378/25/2026
RD27-01 Culvert Replacement - Loma Drive @ MP 0.01Toro EnterpriseJuly 20261$186,342.578/31/2026